Purpose: Water in the Beacon Hill community is supplied by two groundwater wells located on Loudoun Water owned parcels.  Loudoun Water needs to perform maintenance work at these two wells, and to ensure continuous water service to the community, Loudoun Water will activate and connect the reserve well, known as well “I”, to the water system.  Adding well “I” to the system will allow Loudoun Water to perform maintenance work at the existing wells, and will provide operational flexibility and redundancy for the water system.

Project Description:  This project includes all work for placing Well “I” in-service, both at the well site and at the water treatment facility.  Construction at the well site will include grading and site work, installation of new well pump, and a piping connection to the existing raw water main; construction at the water treatment facility will include piping and mechanical upgrades.