This project includes the development of a green field property to include an approximately 3,700 foot-long paved access road, a new 4.8 MGD wet well/dry well type pump station, and an emergency storage tank.  The project also includes the linear utilities necessary for pump station operation, namely; approximately 3,600 feet of force main, 3,000 feet of gravity sewer, 3,600 feet of water main, stormwater culverts, fiber optic extension, and 3-phase power extension.  In addition, the project includes the demolition of the existing sewer pump station and startup and commissioning of the new pump station. Expected to be advertised for bid in the summer of 2022.

Project Status: 
Upcoming Capital Design