Broad Run Water Reclamation Facility Russell Branch Diversion Structure Improvements 
This project includes installation of fiber and power to the Diversion Structure and automatic control valves to allow for remote operation. The construction of this project is expected to be advertised for bid in Spring 2019.

Cedar Crest SPS 1 & 2 Upgrades 
This project includes the site, electrical and mechanical upgrades of two existing sewer pump stations in the Cedar Crest subdivision located in the southern part of Loudoun Water’s Central Service Area. Cedar Crest 1 SPS, originally constructed in 2006, has a capacity of 0.3 MGD. Cedar Crest 2 SPS was originally constructed in 2008 and has a capacity of 0.1 MGD. Improvements at both pump stations will include the replacement of all major equipment, the addition of metering vaults and new security systems. The construction of this project is expected to be advertised for bid in early 2019.

Russell Branch SPS 
This project includes the development of a green field property to include an approximately 3,700 foot-long paved access road, a new 1.15 MGD wet well/dry well type pump station, and an emergency storage tank.  The project also includes the linear utilities necessary for pump station operation, namely; approximately 3,600 feet of force main, 3,000 feet of gravity sewer, 3,600 feet of water main, storm water culverts, fiber optic extension, and 3-phase power extension.  In addition the project includes the demolition of the existing sewer pump station and startup and commissioning of the new pump station. The construction of this project is expected to be advertised for bid in mid-2019.

Goose Creek Emergency Supply Connection
This project includes a 30” HDPE pipeline crossing of the Goose Creek Reservoir, pump station upgrades, and boat ramp construction. The pipe will be placed via open cut for the portions leading up to the reservoir bank and laid along the bottom of the reservoir for the sub-aqueous portion.  The pump station upgrades include removal and replacement of two 400 HP pumps, installation of variable frequency drives for the pumps, a new transformer, a new flow metering vault, a new surge protection valve, and new electrically actuated valving.  The boat ramp construction includes a 1,300 foot-long gravel access road to a concrete apron and 40 foot-long articulated concrete block boat ramp.  The construction of this project is expected to be advertised for bid in early 2019.