September 2018: Project Fact Sheet
July 2018: Customer Letter
March 2018: Water Treatment System Project Progress Schedule
January 2018: Water Treatment System Project Progress Schedule
December 2017: Project Fact Sheet
November 2017: Water Treatment System Project Progress Schedule
September 2017: Water Treatment System Project Progress Schedule
July 2017: Water Treatment System Project Progress
May 2017: Water Treatment System Project Progress Schedule
April 2017: Water Treatment System Project Progress Schedule
February - April 2017: Water Conveyance System Construction Progress Schedule
August 2016: Water Treatment System Project
6/21/2016: Conceptual Design Map
6/13/2016: June 2016 - Construction Progress Schedule
4/26/2016: Mailing to residents on project schedule
1/7/2016: Community Meeting Minutes
10/20/2015: Well Notice Letter
10/14/2015: Summary Notes of Raspberry Falls/Selma Community Meeting
9/25/2015: Community Meeting Presentation
7/21/2015: Summary of Notes of Raspberry Falls/Selma Community Meeting
6/26/2015: Selma Estates and Raspberry Falls Water Supply Systems Public Meeting Presentation
6/1/2015: Resolution of Intent for Selma - Raspberry Availability Fee - Rak - May 14 2015
3/17/2015: Resolution of the Loudoun Water Board Regarding Raspberry Falls and Selma Estates Community Systems
Authorization for Staff to Evaluate Pooling R&R Funding
Presentations from the January 30, 2015 Loudoun Water Board Workshop:
- Study of Long Term Option Review - Aaron Duke
- Raspberry Falls and Selma Estates Community Water Systems, Jonathan Rak
1/23/2015: Raspberry Falls and Selma Estates Community Water Systems Study of Long Term Options